Task |
Responsibility* |
Scheduled Completion Date |
Modified Completion Date |
Comments |
| Display Testing |
BM |
09/08/2005 |
- |
Done |
| Write Serial drivers |
BM |
09/19/2005 |
09/26/2005 |
Done. Both Software RS-232 & USART RS-232 have been written, tested on hyperterminal. |
| Write 1-wire drivers |
SP |
09/26/2005 |
10/03/2005 |
Done |
| Write RF drivers |
TS |
09/26/2005 |
- |
Done |
| Write GPS drivers |
SP |
10/03/2005 |
- |
Done |
| Bluetooth Mobile-Unit drivers |
TS |
10/03/2005 |
- |
Done |
| Bluetooth Base-Station drivers |
TS |
10/10/2005 |
- |
Done |
| Base-Station GUI |
TS |
10/10/2005 |
- |
Done |
| Implement System Power Supply |
BM |
10/17/2005 |
09/19/2005 |
Done. Used the MAX667, which is better than the proposed chip. Design tested, and it regulates +5V very well. |
| System Integration |
TS, SP, BM |
10/17/2005 |
- |
Done |
| System Testing |
TS, SP, BM |
10/24/2005 |
- |
Done |
| Web-site construction |
BM |
10/24/2005 |
10/19/2005 |
Website is up online, and will be updated regularly throughout the project period. |
| Poster Preparation |
TS, SP, BM |
10/24/2005 |
- |
Done |
| Report Writing |
TS, SP, BM |
10/24/2005 |
10/26/2005 |
Report done, using the extra time to make the report better. |
*
TS = Timothy Stotts
BM = Bhushan Mehendale
SP = Shawn Pfister
|