Task
Responsibility*
Scheduled Completion Date
Modified Completion Date
Comments
Display Testing
BM
09/08/2005
-
Done
Write Serial drivers
BM
09/19/2005
09/26/2005
Done. Both Software RS-232 & USART RS-232 have been written, tested on hyperterminal.
Write 1-wire drivers
SP
09/26/2005
10/03/2005
Done
Write RF drivers
TS
09/26/2005
-
Done
Write GPS drivers
SP
10/03/2005
-
Done
Bluetooth Mobile-Unit drivers
TS
10/03/2005
-
Done
Bluetooth Base-Station drivers
TS
10/10/2005
-
Done
Base-Station GUI
TS
10/10/2005
-
Done
Implement System Power Supply
BM
10/17/2005
09/19/2005
Done. Used the MAX667, which is better than the proposed chip. Design tested, and it regulates +5V very well.
System Integration
TS, SP, BM
10/17/2005
-
Done
System Testing
TS, SP, BM
10/24/2005
-
Done
Web-site construction
BM
10/24/2005
10/19/2005
Website is up online, and will be updated regularly throughout the project period.
Poster Preparation
TS, SP, BM
10/24/2005
-
Done
Report Writing
TS, SP, BM
10/24/2005
10/26/2005
Report done, using the extra time to make the report better.


*
TS = Timothy Stotts
BM = Bhushan Mehendale
SP = Shawn Pfister

 

   

 

 