Project Timeline

Milestone Expected Completion Date Actual Completion Date Comments Completed By
DC Motor Testing 8/20/2005 8/20/2005 Complete Both
Encoder Testing 8/25/2005 8/25/2005 Complete MW
Front End Analog Schematic 9/1/2005 9/1/2005 Complete PO
Front End Analog IC Creation 9/14/2005 9/19/2005 Complete MW
User Interface Creation in VB 9/12/2005 9/12/2005 Complete PO
Choosing Proper A/D 8/27/2005 8/27/2005 Complete PO
Project Proposal 9/7/2005 9/7/2005 Complete Both
Design Review Presentation 9/12/2005 9/11/2005 Complete Both
Encoder Mount 9/21/2005 9/21/2005 Complete PO
Photodiode Mount 9/22/2005 9/22/2005 Complete MW
Start Web Site 9/19/2005 9/16/2005 Complete Both
ActiveX Programming 9/25/2005 10/26/2005 Complete PO
User Interface Interfacing 9/30/2005 10/26/2005 Complete Both
Creating Test Environment 10/4/2005 --- Complete Other
System Testing with All Parts 10/10/2005 10/26/2005 Complete Both
Testing of Final Project 10/14/2005 10/26/2005 Complete Both
Project Poster Completion 10/16/2005 10/26/2005 Complete Both
Overall Completion Date 10/20/2005 10/26/2005 Complete Both
Project Report 10/23/2005 10/26/2005 Complete Both