Complete
In Progress
Behind Schedule (according to the modified completion date...it'd all be red otherwise!!)

Project Schedule

Description

Primary Team Member

Scheduled Completion Date

Modified Completion Date

Comments

Preliminary Website Design

BMA

12/7/04

12/7/04

Complete

Sensor Network

BMA

12/14/04

2/1/05

1-Wire Implementation failed, using multiplexers

Reflex Coding

BMA

12/14/04

12/21/04

Rev1-3 Complete

Logic Coding

JDW

12/21/04

1/4/05

Rev1-2 Complete

Building Base

JDW

12/28/04

1/25/05

Complete

Testing – Path Following

JDW

1/4/04

1/25/05

Complete

Bug Fixing – Path Following

BMA

1/4/04

1/25/05

Complete

Testing – Obstacle Avoidance

BMA

1/11/05

2/8/05

Complete

Bug Fixing – Obstacle Avoidance

JDW

1/11/05

2/8/05

Complete

Testing – Full Project

JDW

BMA

1/18/05

2/8/05

 

Bug Fixing – Full Project

BMA

JDW

1/18/05

2/8/05

 

Testing – Final Verification

JDW

BMA

1/25/05

2/1/05

Removed due to scheduling conflicts - will be incorporated into Testing-Full Project

Final Report

JDW

2/8/05

2/8/05

 

Poster

BMA

2/8/05

2/8/05

 

Website

BMA

2/8/05

2/8/05

Complete, save for updates.

Demo

BMA

JDW

2/8/05

2/8/05

 

Progress Reports

12/07/04
12/14/04
1/4/05
1/11/05
1/18/05
1/25/05
2/1/05