Complete
In Progress
Behind Schedule (according to the modified completion date...it'd all be red
otherwise!!)
Project Schedule |
||||
|
Description |
Primary Team Member |
Scheduled Completion Date |
Modified Completion Date |
Comments |
|
Preliminary Website Design |
BMA |
12/7/04 |
12/7/04 |
Complete |
|
Sensor Network |
BMA |
12/14/04 |
2/1/05 |
1-Wire Implementation failed, using multiplexers |
|
Reflex Coding |
BMA |
12/14/04 |
12/21/04 |
Rev1-3 Complete |
|
Logic Coding |
JDW |
12/21/04 |
1/4/05 |
Rev1-2 Complete |
|
Building Base |
JDW |
12/28/04 |
1/25/05 |
Complete |
|
Testing – Path Following |
JDW |
1/4/04 |
1/25/05 |
Complete |
|
Bug Fixing – Path Following |
BMA |
1/4/04 |
1/25/05 |
Complete |
|
Testing – Obstacle Avoidance |
BMA |
1/11/05 |
2/8/05 |
Complete |
|
Bug Fixing – Obstacle Avoidance |
JDW |
1/11/05 |
2/8/05 |
Complete |
|
Testing – Full Project |
JDW BMA |
1/18/05 |
2/8/05 |
|
|
Bug Fixing – Full Project |
BMA JDW |
1/18/05 |
2/8/05 |
|
|
|
|
|
|
Removed due to scheduling conflicts - will be incorporated into Testing-Full Project |
|
Final Report |
JDW |
2/8/05 |
2/8/05 |
|
|
Poster |
BMA |
2/8/05 |
2/8/05 |
|
|
Website |
BMA |
2/8/05 |
2/8/05 |
Complete, save for updates. |
|
Demo |
BMA JDW |
2/8/05 |
2/8/05 |
|
Progress Reports